Reading: Abandoned Zaka Econet booster construction resumes
Share
Notification Show More
Font ResizerAa
TellZim NewsTellZim News
Font ResizerAa
  • Home
  • Elections & Governance
  • Service Delivery & Accountability
  • Women & Youth Empowerment
  • More
Search
  • Home
  • Elections & Governance
  • Service Delivery & Accountability
  • Women & Youth Empowerment
  • More
    • Human Rights
    • Climate Change & Environment
Follow US
© 2024 TellZim News. All Rights Reserved.
TellZim News > Blog > Service Delivery & Accountability > Abandoned Zaka Econet booster construction resumes
Service Delivery & Accountability

Abandoned Zaka Econet booster construction resumes

TellZim News
Last updated: May 14, 2024 12:56 pm
TellZim News
Share
4 Min Read
SHARE

By Brighton Chiseva

Zaka – Mobile network giant Econet Wireless has started works for the construction of a booster near Jecha Business Centre, in Chief Nhema area after the project was abandoned a few months ago on allegations of clashes between Zanu PF and Citizens Coalition for Change (CCC).
Work was supposed to have started beginning of November in 2023 but work only started on May 08 2024 to the delight of locals who were bearing the brunt of limited access to mobile networks.
Ward 15 Councillor Simon Chakazani confirmed the latest development and said they were happy with the progress and were hoping that work would be completed early.
“I can confirm that work has started and we are happy as a community that we are finally going to get a network which has been a challenge in the area for some time.
“We hope that it will be completed soon as people can no longer wait to enjoy the connectivity. People used to travel to higher grounds for better communication and often people missed important updates in time because we had no network,” said Chakazani.
Sources had earlier told TellZim News that they suspected Econet could have been put off by political interference where the local headman was accused of having tried to bar a perceived CCC member amongst the contractors.
It was also alleged that the traditional leaders had demanded an undisclosed amount of cash for the booster to be constructed.
Econet engineers were said to have asked if they were going to employ manual workers from homesteads surrounding the site and that is where one Obvious Kwenda was seconded but the local headman went on to report to Zanu PF district officials that Econet had employed a CCC member.
Contacted for comment earlier Kwenda said he was approached by several Zanu PF members who told him that the local party leadership was not happy with him being part of those contracted by the telecoms giant.
“I was approached by several Zanu PF members who told me that they had meetings where I was discussed with the leadership questioning why I was among those nominated to work on the project.
“I am not even sure if I am going to work when they come because we were told that work would start on November 1 but up to now there is nothing and we are still waiting. I am eager to work and this has nothing to do with political orientation,” said Kwenda.
However, sources said Kwenda was among the workers when work resumed at the construction site.
Last year, a highly placed source from Econet however said work was in progress offsite at the time, saying there was some progress and the project was on course with a completion target of April 2024.
“Work is ongoing as we speak, the target is completing the project by April next year. So what happens is people may see no progress on the ground but work is ongoing offsite. Maybe material is being collaged for shipping once, so that work can start once the needed material has been placed on site to avoid ups and downs,” said the source at the time.

You Might Also Like

Masvingo City admits using substandard paint for road markings

Masvingo South directs CDF towards health, education

Runyararo Clinic maternity wing on cards

Government to end Tongaat Milling monopoly – Minister Ndlovu

Chiredzi High goes beyond books, donates to Chingele Children’s home

Sign Up For Daily Newsletter

Be keep up! Get the latest breaking news delivered straight to your inbox.
[mc4wp_form]
By signing up, you agree to our Terms of Use and acknowledge the data practices in our Privacy Policy. You may unsubscribe at any time.
Share This Article
Facebook Twitter Copy Link Print
Share
Previous Article Morgenster Mission Hospital gets US$171k from Latter Day Saints
Next Article 16-year-old Chivi boy murders cousin (4)
Leave a comment Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Stay Connected

FacebookLike
TwitterFollow
InstagramFollow
YoutubeSubscribe
TiktokFollow
- Advertisement -
Ad imageAd image

Latest News

Masvingo City holds induction workshop for SDCs
Service Delivery & Accountability May 22, 2025
Chiredzi man drowns in canal
News May 22, 2025
Teen drowns while bathing
News May 22, 2025
Shurugwi man killed over plate of Sadza
News May 22, 2025
TellZim NewsTellZim News
Follow US
© 2024 TellZim News. All Rights Reserved.
adbanner
AdBlock Detected
Our site is an advertising supported site. Please whitelist to support our site.
Okay, I'll Whitelist
Welcome Back!

Sign in to your account

Lost your password?