ZW $100 million devolution boost for Mucheke Trunk Sewer

Date:

Share post:

…As contractor resumes operations on the project

Melinda Kusemachibi

The ‘legacy’ Mucheke Trunk Sewer project that has been going on since 2013 received a major boost towards resumption of operations following the injection of ZW$100 million devolution funds, Masvingo Town Clerk Engineer Edward Mukaratirwa recently confirmed.
Mukaratirwa indicated that they are going to cover an area of 2km using the devolution funds allocated this year.
“ZW$100 million was allocated for working on the trunk sewer project and it will cover an area of 2km,” said Eng Mukaratirwa.
He also said that contractors were on the ground as they resume work on the project to try and cover the area.
“Contractors are on the ground as they have resumed work. They were supposed to have started early February but they were affected by rains, now the project has resumed,” said Mukaratirwa.
Masvingo city’s Mucheke Trunk Sewer upgrade remains incomplete, nine years after the project started, and more than US$4 million was initially lost towards the project.
Mukaratirwa said of the ZW$120million allocated in 2021 they only used ZW$87million.
“In 2021 ZW$120 million was allocated on devolution funds towards Mucheke Trunk Sewer but we only used ZW$87 million and covered a distance of 1,2km,” said Eng Mukaratirwa.
In 2012, City of Masvingo advertised a tender to construct the Mucheke Trunk Sewer, a pipeline running roughly parallel to Mucheke River and planned to link with the sewer plant in Eastvale.
Covering a stretch of 7km, the new sewer trunk is meant to extend to the fairly new and sprawling Victoria Ranch suburb just outside Masvingo.
Initially Harare-based Mutual Construction (Pvt) Ltd was awarded the tender after beating at least 10 other bidders, and council fixed a US$2,1 million loan from the National Social Security Authority (NSSA) to fund the project.
As at March, 3 2021 checks have however, revealed that Mutual Construction was not among the 108 professional firms listed on the Engineering Council of Zimbabwe (ECZ) website.
Project development kicked off in 2012 and was supposed to be completed within a year, but work stopped in early 2013.
Mutual Construction had removed its equipment that remained on the project site by the end of 2014, save for the giant 750-1200mm diameter cement-asbestos pipes purchased from Turnall Holdings.
In 2015, council put out a public notice borrowing a further US$1, 7 million to fund resumption of work on the project. But barely a quarter of the job has been done.
According to a recent report, Masvingo reported an average of 2 812 sewer blockages per year and was blamed for lack of supervision and lack of enforcement of contract agreements by its engineers and staff.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Related articles

Zaka High learner unveils P2M Smart Industrial Hub at Harare Agricultural Show

By Staff ReporterZAKA – A Form Six science learner from Zaka High School, Progress Munashe Mtisi, whomade headlines in...

Community efforts stall as 42 bags of cement vanish at Bikita Clinic Project

Beverly BizekiBIKITA – A cloud of suspicion hangs over the Mapovomovo Clinic project in Bikita West,Ward 9, after 42...

Chigarapasi Beerhall on life support, Kurauone calls for urgent overhaul

By Beatific Gumbwanda CHIREDZI – Chigarapasi Beerhall, once the beating heart of social and economic life in Chiredzi, is on...

A peep into the newly appointed 10 Senators…

Tagwirei unstoppable as ED consolidates more powers   Valerio Sibanda, Tungwarara left out By Brighton Chiseva President Emmerson Mnangagwa has moved swiftly to implement the dictates of the Constitutional Amendment Act, appointing...